Village Schedule � Week of 10/5

2300 EAST � East Side: Work in this area will include the sidewalk and pedestrian ramp in the vicinity of Unpredictable as well as the Phylden area.

EAST END OF MURRAY HOLLADAY RD: Curb & Gutter on the east end is scheduled for Tuesday. Sidewalk in front of Relics is scheduled for Wednesday.

HOLLADAY BLVD � SOUTH END (West Side): Concrete paving from Meir�s to Holladay Pharmacy is scheduled for early in the week. Drive approaches will be constructed serving the transmission shop and Meir�s.

NORTHWEST CORNER OF MURRAY HOLLADAY ROAD and HOLLADAY BLVD.: This section of roadway will be demolished and cleared. Strom drain improvements will be completed and curb & gutter poured. Pavement for this corner is currently scheduled for Friday and Monday of the next week.

TRAFFIC SIGNAL: The new traffic signal at Holladay Blvd. and Murray Holladay Road is scheduled to be placed on Thursday / Friday of this week.

  • This mailing list is a public mailing list - anyone may join or leave, at any time.
  • This mailing list is announce-only.

Stay Informed of the progress, maintenance and construction updates in the City of Holladay. The improvements will be be beautiful. During our construction, this e-mail list will help you navigate through our improving city.

Privacy Policy:

Privacy Statement

Your privacy is important to us. The City of Holladay will only use your contact information to keep you informed about official city business and activities. The city will never sell or provide your information to anyone outside of the city.