North end of Holladay Blvd: The ribbon cutting for this area was on August 18th. We appreciate those who were able to attend and participate in this event. Work this week will include general clean-up, and construction of remaining driveways and approaches.
South end of Holladay Blvd: Work in this area this week will include sidewalk, on-street parking (in the area of Relics), and driveway construction. Concrete on-street parking is scheduled to be placed on Thursday or Friday of this week. Construction is scheduled to switch to the west side of the road in 2 weeks. There will continue to be no left turn from northbound Holladay Blvd. onto Murray-Holladay Road. Arbor Lane is the alternate route to allow traffic to go westbound on Murray-Holladay.
East end of Murray-Holladay Road: ATMS signal wiring is being placed along the north side of the road. Other work in this area includes construction of irrigation and street lighting conduit. One week from Tuesday, the traffic is scheduled to be switched to the opposite side of the road and limited to one-way (west-bound) to accommodate restricted construction safety clearances.
West end of Murray-Holladay Road: Work will continue on sidewalks, driveways and curb & gutter on the south side. Asphalt paving is scheduled for next week.
2300 East: Work along the east side of the road this week will include irrigation and water connections. Concrete paving immediately north of Murray-Holladay Road is scheduled for Thursday or Friday of this week.
Traffic Signal: The traffic signal at Laney and 2300 east is fully functional.
Street Lights: Street light bases and electrical work is largely complete. Street light poles are currently being fabricated.